LXP House Update: Baby Steps to Completion
It has been a journey that has tested our faith, and our patience at times, and it is with immense gratitude that we see a chapter of our lives come to a close; we completed the last big step in constructing the LXP House! Last month we were able to install the flooring and we … Continue reading
Ceilings are in!
We are ecstatic to report that another phase of construction has been completed at the LXP House; ceilings have been installed throughout the house and the result is stunning. The ceilings have made such a difference in our lives, both by insulating us from the freezing winter temperatures outside and increasing the privacy and comfort of … Continue reading
Moving In and Moving Forward
It’s official! As of the 17th of October the LXP House at the LXP Base is open for business living life! We are thrilled the share this testimony of God’s faithfulness as we have realised our long time goal of moving into the LXP House and shifting our centre of life and ministry to the … Continue reading
LXP House: Countdown to Move-In Begins
It is hard to believe 19 months have passed since the foundation lines for the LXP House were marked off on the bare ground at the LXP Base. The past month and a half has been an exciting time of seeing the realization of our dream to complete the house and move to the Base … Continue reading
Roof and Electrical Wiring Complete
In April the roofing and electrical wiring were completed on the house! Once doors and windows are installed, they can connect our house to the power grid. Move in day is getting closer!
Roofing Continues on the LXP House
The past three weeks have seen huge progress in roofing at the house. It has also been a season of trusting the Lord for breakthrough. We purchased all the materials needed for the project before the roofers arrived. However, the metal roofing sheets were on back order from the supplier and it appeared they would not … Continue reading
Roofing the LXP House!
Ten months ago, in May 2013, the walls of the LXP House were completed. Since that time we have been excitedly anticipating the next phase in the building project: the roof. Last Monday the wait was over and we began roofing! We are so thankful to be taking this big step and trust that the roof … Continue reading
Building Progress – Foundation
We are making excellent progress with the building project at the LXP Lesotho base. We wanted to share the latest accomplishments and some progress pics. Water: The machine that is digging for our water supply is still noisily and busily working away at the bore hole, which has passed the 30 meter mark. It’s slow … Continue reading